<> <> <> <<>> <<>> Milestones Plan Date Display board complete 1/14 nMos LP tested 2/16 CMOS PCB complete 3/6 MI chip completed 3/9 Proc. completed 4/17 MI back from fab 5/4 MI tested 6/5 Proc. back from fab 6/19 Proc tested 7/17 Final Board tested 7/31 Proto. to software 8/7 Revised proc. complete 8/14 Proc. 2 back from fab 10/16 Proc. 2 tested 10/30 Final proto to software 11/2