PSSR87.tioga
Mark Ross January 16, 1987 8:11:36 am PST
Last Edited by: Ross January 16, 1987 8:22:52 am PST
Milestones Plan Date
Display board complete 1/14
nMos LP tested 2/16
CMOS PCB complete 3/6
MI chip completed 3/9
Proc. completed 4/17
MI back from fab 5/4
MI tested 6/5
Proc. back from fab 6/19
Proc tested 7/17
Final Board tested 7/31
Proto. to software 8/7
Revised proc. complete 8/14
Proc. 2 back from fab 10/16
Proc. 2 tested 10/30
Final proto to software 11/2